20191117 Space move 2019
Jump to navigation
Jump to search
Whats new?
- Network & Internet Severin
- 100m network cable has been ordered and we are allowed to route that though the office of Neo and our old space
- Electricity Nico
- Bernhard is talking to Nico about additional power sockets
- RecyclingCenter David
- Will be smaller, more specialized, to be determined after it is clear where it'll be placed
- Storage Paul
- Paul not present
- Gaming&Relax AdrianM
- Flipper topic
- Electronics Paul and German
- new size is online, maybe extende the wall with the shelves
- Workshop Bernhard
- We need the plan for the room (housing, not the internals) asap!
- material will be moved out of the workshop
- two sockets for drill press and CNC
- Lasercutter Bernhard
- Tube and PSU should be bought in the next time
- How to connect the exhaust air?
- 3D-Printing AdrianM
- foldable table within the Laser/3D-room
- Kitchen PeterM + Theresa
- new plans in the drive
- fridge position might move
- Community Annika
- Nico didn't receive the size yet so he wasn't able to calculate the needed wood yet
- We will decide if we build a platform in the Plenum on November 24th (as quite some costs are involved)
- Door David
- Current lock fits, so the current system can be moved without major problems.
- Parking
- will be discussed after the move
Worklog since last meeting
- Pit is clean now
- Ramp has been filled with concrete
- Frame around the gates have been sealed with construction foam to avoid cold air coming in
- Old space wooden wall near door is now free of obstacles. Everything has been disassembled and put on pallets
Open Decisions
- Do we want a platform in the community area? Decision will be postponed to the Plenum on November 24th
ToDos
- Clarify if we can remove the concrete block in front of the pit and the door - David
- David will discuss this with MGH
- Clarify if we can remove the steel edge on the pit - David
- David will discuss this with MGH
- Fix all holes and damaged places in the inside walls (outside would be an addition achievement!)
- Will be done when we do the plastering of the brick wall
- Replace metal grids with something closed
- Best shot seems to be two layers of OSB 22mm + 18mm to get 40mm - There are 40mm sheets but 22 and 18 are readily available and cheaper
- Paint the inside walls up to the cable canal once they have been prepared (brick and fresh plaster need priming!)
- Install power cables and connect them (two tasks)
- Install Network cabling
- Cleanup