== Decision about the pit and a platform == | == Decision about the pit and a platform == | ||
There are two ideas about the Pit: | There are two ideas about the Pit: | ||
* Build a platform above the pit which will raise the ceiling down there | |||
** A LOT of work and it will cost about 1000€ | |||
** More space in the middle of the pit so you can walk down there | |||
** An even floor in the main community area | |||
** We can route cables underneath the floor | |||
** Will limit our ability to move pallets around | |||
* Remove the metal border around the pit and make it more or less even | |||
** Easy to do | |||
** Cheap | |||
** Space should be enough down there | |||
Both have advantages. Let's decide. | Both have advantages. Let's decide. | ||
For extremely tall or | For extremely tall or disabled people we can also have space for a few boxes in the main space. | ||
We'll not build a platform. If the city decides that we absolutely can't remove the metal ridge we'll redecide. | We'll not build a platform. If the city decides that we absolutely can't remove the metal ridge we'll redecide. | ||
[[Category:Plenum]] | [[Category:Plenum]][[Category:Minutes]] |
Latest revision as of 14:18, 21 November 2020
Topics for the Plenum
What are you currently working on?
Tell everyone about your current projects and stuff you've done for the space
- Christoph: Space move
- Theresa: Space move
- Jonas: Umzug
- Paul: Umzug
- Nico: Space move and a smart mirror
- Andreas: Umzug (specifically using a broom)
- Rene: Shitposting
- Bernhard: Space Move
- Adrian: Repairing the Plotter and move
- Annika: Lasercutting Christmas stuff and space move
- Severin: PP, LoraWAN and space move
- David: Talking to the city about our space move
Say Thank you
Let's say thank you to those who did some awesome stuff for the space since the last plenum
- Nico for making the lab $$$$ by selling the roller conveyor thing on ebay-kleinanzeigen!
- Everyone who is using smile.amazon.de - that brought us 22,77€ from July till September
- David for managing things to do with the city
- Christoph for painting the walls in the new space
- Concrete-Team who spend a day mixing and pouring concrete
- Everyone for aggregating our stuff and cleaning up a bunch
- David for ordering new drinks
- German, Nico and Andreas for driving to the hardware store a bunch of times
- Andreas for getting a concrete mixer to our new space
- Everyone else we've forgotten
- Severin, German and Christoph for clearing a path for our new infrastructure
Stuff from the past
What was discussed at the last Plenum? What's the current status of those things? 20191114 Plenum
- Nothing new regarding Werkbox3
- Tools are missing but we decided to order boxes for a better organisation - group order ends tomorrow
- Somebody needs to plan the christmas party on the 5th of december, but it's definitely going to happen
- We now have a metal band saw
- The doorlock we have fits the new door so we don't need to spend another 300-800€
Anything you don't feel comfortable within the space? What would you like to change or to be changed?
Is there anything that's bothering you?
- Alex CNC - Space for the machine was approved but it now uses 2m of additional desk space for a multi monitor PC, a lot of our tools are lying around, 4square meters of floor are covered in metal scrap, ...
=> Bernhad will talk it out with Alex
- Threatment of private tools - People are bringing their private tools so please threat them carefully
- Always the same few people helping at the move
The new space
- So far we've officially spent 900€ on the move
- The wood and metal workshop started moving to the new space
- We've got a signed rent contract now
- David is trying to get us registered as a "culturally worthwhile" rent party which would possibly help us with stuff like rent cuts
Things to Buy
Things to buy for projects related to the space.
- 60€ for a power supply station for for the soldering station => approved
- 120€ for a network cabinet => approved
- 100€ for backbords for the new kitchen => approved
Decision about the pit and a platform
There are two ideas about the Pit:
- Build a platform above the pit which will raise the ceiling down there
- A LOT of work and it will cost about 1000€
- More space in the middle of the pit so you can walk down there
- An even floor in the main community area
- We can route cables underneath the floor
- Will limit our ability to move pallets around
- Remove the metal border around the pit and make it more or less even
- Easy to do
- Cheap
- Space should be enough down there
Both have advantages. Let's decide. For extremely tall or disabled people we can also have space for a few boxes in the main space. We'll not build a platform. If the city decides that we absolutely can't remove the metal ridge we'll redecide.