20191117 Space move 2019

From The Munich Maker Lab's Wiki
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.

Whats new?

  • Network & Internet Severin
    • 100m network cable has been ordered and we are allowed to route that though the office of Neo and our old space
  • Electricity Nico
    • Bernhard is talking to Nico about additional power sockets
  • RecyclingCenter David
    • Will be smaller, more specialized, to be determined after it is clear where it'll be placed
  • Storage Paul
    • Paul not present
  • Gaming&Relax AdrianM
    • Flipper topic
  • Electronics Paul and German
    • new size is online, maybe extende the wall with the shelves
  • Workshop Bernhard
    • We need the plan for the room (housing, not the internals) asap!
    • material will be moved out of the workshop
    • two sockets for drill press and CNC
  • Lasercutter Bernhard
    • Tube and PSU should be bought in the next time
    • How to connect the exhaust air?
  • 3D-Printing AdrianM
    • foldable table within the Laser/3D-room
  • Kitchen PeterM + Theresa
    • new plans in the drive
    • fridge position might move
  • Community Annika
    • Nico didn't receive the size yet so he wasn't able to calculate the needed wood yet
    • We will decide if we build a platform in the Plenum on November 24th (as quite some costs are involved)
  • Door David
    • Current lock fits, so the current system can be moved without major problems.
  • Parking
    • will be discussed after the move

Worklog since last meeting

  • Pit is clean now
  • Ramp has been filled with concrete
  • Frame around the gates have been sealed with construction foam to avoid cold air coming in
  • Old space wooden wall near door is now free of obstacles. Everything has been disassembled and put on pallets

Open Decisions

  • Do we want a platform in the community area? Decision will be postponed to the Plenum on November 24th


ToDos

  • Clarify if we can remove the concrete block in front of the pit and the door - David
    • David will discuss this with MGH
  • Clarify if we can remove the steel edge on the pit - David
    • David will discuss this with MGH
  • Fix all holes and damaged places in the inside walls (outside would be an addition achievement!)
    • Will be done when we do the plastering of the brick wall
  • Replace metal grids with something closed
    • Best shot seems to be two layers of OSB 22mm + 18mm to get 40mm - There are 40mm sheets but 22 and 18 are readily available and cheaper
  • Paint the inside walls up to the cable canal once they have been prepared (brick and fresh plaster need priming!)
  • Install power cables and connect them (two tasks)
  • Install Network cabling
  • Cleanup